Logopark AlmatyA3 highway × BAKAD junction
Aerial view of the site: column grid, mobile crane and the access road beside BAKAD

Status as of 12 November 2026

Construction progress

SiteIn progress

Access road to the site

The site seen from the access road: the asphalt and lane markings are in place and lighting columns have been installed along the plot. Beyond the fence, rows of rebar starters and the monolithic columns of phase one are visible.

Access road · 0:24
Frame

Monolithic column erection

A mobile crane is lifting formwork onto the next monolithic column while the crew works alongside it. The phase-one column grid is taking its design geometry; foundation cap concreting and utility installation continue in parallel.

A mobile crane lifting formwork onto a monolithic column, surrounded by the column grid
Site footage · 0:22
Site footage · 0:10
Quality control

Concrete quality control

Concrete cores have been taken for laboratory strength testing. Sample testing is a mandatory acceptance step for monolithic structures before formwork is struck and work fronts are handed over.

A concrete core sample taken for laboratory strength testingCore sample: aggregate structure visible on the side
Foundations

Pouring foundation caps

Freshly poured foundation cap concrete with rebar starters: once it reaches design strength, the frame columns will be installed on these supports. Work proceeds in sequential bays.

Freshly poured foundation cap concrete with rebar starters
Utilities

Utility networks under way

An aerial view shows the regular grid of foundation blocks with rebar starters. In parallel, a cable trench has been prepared and cable drums delivered — installation of the external power supply network is starting.

Aerial view, 3 November: a regular grid of foundation blocks with rebar starters
Utility trench marked with safety tapeWooden cable drums delivered before cable laying
Site

The site from the air: the column grid grows

Aerial photography records the growing number of installed columns and foundations. An operating warehouse already stands next to the plot — the new complex is joining an established logistics zone beside BAKAD.

Aerial view, 27 October: column grid, mobile crane and access roadAerial view, 27 October: rows of foundation caps and an operating warehouse beyond the road
Frame

Columns and axis surveying

Some monolithic columns are already cast, others remain in formwork and rebar cages. A total station is on site to set out and check axes before the next frame elements are erected.

Monolithic columns: some cast, others in formwork and rebar cagesA total station on a tripod: checking column axes
Foundations

Foundations and the first columns

Aerial views show the foundation cap grid and a long utility trench, alongside the first installed columns. From the ground: modular formwork, rebar cages and a mobile crane at work — the site has moved from earthworks to frame erection.

Aerial view, 20 October: foundation cap grid and a long trenchAerial view, 20 October: first columns and a mobile craneAerial view, 20 October: the building footprint with column and foundation gridsAerial view, 20 October: rebar cages, formwork and rows of foundation caps
Mobile crane installing columns, a worker in a hard hat in the foregroundModular column formwork with guy lines against the sky
Site

Current works status — 30 September 2026

Frame erection is under way: cranes are setting columns along the grid, and some of the columns are already concreted. Utilities are being laid in parallel, and an access road is being built along the plot.

Aerial view of the site: column grid, mobile crane and aerial work platform installing columns30 September 2026
Site

Status as of 25 September 2026

Column installation is under way: concreting in formwork, columns in place and rebar cages. The site entrance and site compound are in place.

Site

Status as of 15 September 2026

Foundation works continue: the pocket grid is complete, column rebar cages are being installed and ground-beam cages are assembled. A footpath is being laid along the access road.

Site

Status as of 18 August 2026

Earthworks, utilities installation and foundation pockets were under way on site.

The site on 18 August 2026: overview, pipeline installation, earthworks, foundation pocket grid, reinforcementAugust 2026
Construction startIn progress

Phase A — 62 714 m²

First phase of the warehouse complex. Completion — Q3 2027. Deal formats: lease and built-to-suit.