Griffin Partners
Status as of 12 October 2026

Construction progress

Schedule
Phase A
Start: Q2 2026Completion: end of Q2 2027
12 October 2026
Site
In progress

Current works status — 12 October 2026

Frame installation continues: rows of columns are already standing on the grid, and cranes are setting rebar cages. Foundation reinforcement and the pipeline proceed in parallel. The access road along the plot is already paved.

30 September 2026
Site

Status as of 30 September 2026

Frame installation is under way: cranes are setting columns across the grid, some piers are already in concrete. Utilities are being laid in parallel, and the access road along the plot is being paved.

25 September 2026
Site

Status as of 25 September 2026

Column installation is under way: concrete pours in formwork, erected piers and rebar cages. The site entrance and compound are in place.

15 September 2026
Site

Status as of 15 September 2026

Foundation works continued: the pocket grid was in place, column cages were being installed, grade-beam cages assembled. Pavement was being laid along the access road.

August 2026
Site

Status as of 18 August 2026

Earthworks, utilities installation and foundation pockets were under way on site.

Q2 2026
Construction start
In progress

Phase A — 62 714 m²

First phase of the warehouse complex. Completion — end of Q2 2027. Deal formats: lease and built-to-suit.

Leasing enquiries
Roman Fotiev

Roman
Fotiev

Executive Director
Griffin Logopark Almaty